With sunny and warmer weather this week, I was able to complete the subfloor before ALTAR. It doesn't look like much, but the flashing, insulation, and trailer-related items took more time than I had anticipated.
Day 10: Fixed a mistake (I forgot the exterior storage had an open bottom),
cut some studs for front and rear wall framing.
Day 9: Glued and nailed down subfloor sheathing,
applied Rust Reformer to trailer bottom.
Day 8: Registered trailer, cut final insulation panels, spray foamed gaps in insulation,
cut Advantech subfloor sheathing.
Day 7 (short day): Cut more insulation.